# Hunter Industries, LTD.: TxDOT widen non-freeway contract 86% complete, FM 3349, Williamson County ($5,508,593, 6 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | Diibs Specialists, LLC (0.69%); D. I. J. Construction, INC. (2.31%); Murray Construction (0.35%); Rucoba & Maya Construction, LLC (19.51%); Superior Traffic Control, LLC (0.36%); Texas Environmental Management - San Antonio, INC. (2.56%) |
| Progress | 86.22% complete, 80.39% of time used |
| Amount | $5,508,593 revised (original $4,662,191) |
| Change orders | $754,900 |
| Paid to date | $4,670,427 |
| Work | Widen Non-Freeway |
| Location | FM 3349, CR 404 to FM 1660, Williamson County, Austin District |
| Let / began | 2025-06-05 / 2025-10-06 |
| Latest estimate | 2026-10-05 |
| Contract number | 6253208 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.