# Hunter Industries, LTD.: TxDOT rehabilitation of existing road contract 57% complete, US 83, Dimmit County ($46,516,774, 8 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | Professional Traffic Control LLC (0.06%); 4e Tree Worx LLC (0.1%); Murray Construction (0.2%); Scr Civil Construction, LLC (0.22%); D&G Energy Corporation (0.95%); Highway Barricades And Services, LLC (1.38%); Centerline Technologies, LLC (0.14%); K. L. Durham Construction, L.L.C. (0.08%) |
| Progress | 57.3% complete, 52.27% of time used |
| Amount | $46,516,774 revised (original $46,859,660) |
| Change orders | $-342,886 |
| Paid to date | $26,652,968 |
| Work | Rehabilitation Of Existing Road |
| Location | US 83, 1.741 MI SOUTH OF FM 2688 to WEBB/DIMMIT CO LINE (SURVEYED MONUM, Dimmit County, Laredo District |
| Let / began | 2024-07-09 / 2024-12-09 |
| Latest estimate | 2026-10-02 |
| Contract number | 7243004 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.