# Hunter Industries, LTD.: TxDOT widen non-freeway contract 90% complete, SH 80, Gonzales County ($15,132,052, 7 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | Murray Construction (0.2%); Professional Traffic Control LLC (0.09%); Texas Guardrail Contractors LLC (7.77%); South Texas Traffic Alliance INC. (0.14%); Interstate Barricades & Markings, INC. (3.04%); J. H. Oden Contracting Company (0.7%); 4e Tree Worx LLC (0.81%) |
| Progress | 90.27% complete, 118.33% of time used |
| Amount | $15,132,052 revised (original $14,520,546) |
| Paid to date | $13,108,303 |
| Work | Widen Non-Freeway |
| Location | SH 80, GUADALUPE C/L to US 90A, Gonzales County, Yoakum District |
| Let / began | 2024-07-10 / 2024-10-24 |
| Latest estimate | 2026-10-05 |
| Contract number | 7243204 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.