# Hunter Industries, LTD.: TxDOT maintenance contract 88% complete, FM0394, Kerr County ($2,627,176)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Progress | 87.75% complete, 96.4% of time used |
| Amount | $2,627,176 revised (original $1,284,271) |
| Change orders | $1,312,905 |
| Paid to date | $2,279,118 |
| Work | Maintenance |
| Location | FM0394, SL 98 to SH 27, Kerr County, San Antonio District |
| Let / began | 2025-07-31 / 2025-07-30 |
| Latest estimate | 2026-10-06 |
| Contract number | 7252626 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.