# Hunter Industries, LTD.: TxDOT widen non-freeway contract 100%+ complete, US 59, Victoria County ($57,741,312, 11 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | Texas Environmental Management - San Antonio, INC. (0.63%); Highway Barricades And Services, LLC (0.81%); Vaca Underground Utilities INC (1.49%); J&R Contracting Services, INC. (1.72%); Murray Construction (0.18%); Jb Pinnacle Group, LLC (1.66%); Sk Concrete Services LLC (0.01%); A. H. Beck Foundation Co., INC. (1.1%); Cat Skinner, LLC (0.2%); Toro Bravo Construction, LLC (0.06%); 4e Tree Worx LLC (0.18%) |
| Progress | 100.33% complete, 99.44% of time used |
| Amount | $57,741,312 revised (original $55,933,078) |
| Change orders | $425,622 |
| Paid to date | $56,543,840 |
| Work | Widen Non-Freeway |
| Location | US 59, BU 59-T to BU 77S, Victoria County, Yoakum District |
| Let / began | 2023-08-02 / 2023-11-20 |
| Latest estimate | 2026-10-05 |
| Contract number | 8233003 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.