# Hunter Industries, LTD.: TxDOT widen non-freeway contract 92% complete, SH 72, Dewitt County ($75,962,747, 7 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | 4e Tree Worx LLC (0.39%); Highway Barricades And Services, LLC (1.01%); Murray Construction (0.14%); Jb Pinnacle Group, LLC (1.02%); Texas Environmental Management - San Antonio, INC. (0.52%); Third Coast Services LLC (1.1%); Eggemeyer Land Clearing, LLC (0.64%) |
| Progress | 92.28% complete, 89.2% of time used |
| Amount | $75,962,747 revised (original $74,026,222) |
| Change orders | $-639,388 |
| Paid to date | $67,724,333 |
| Work | Widen Non-Freeway |
| Location | SH 72, FM 237 to US 87, Dewitt County, Yoakum District |
| Let / began | 2023-08-03 / 2023-12-08 |
| Latest estimate | 2026-10-05 |
| Contract number | 8233204 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.