# Hunter Industries, LTD.: TxDOT maintenance contract 68% complete, IH0010, Gonzales County ($2,922,699, 2 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | Trp Construction Group, LLC (3.94%); A K Fuquay Construction (1.18%) |
| Progress | 67.96% complete, 64.11% of time used |
| Amount | $2,922,699 revised (original $2,922,697) |
| Paid to date | $1,986,195 |
| Work | Maintenance |
| Location | IH0010, DISTRICT WIDE to ., Gonzales County, Yoakum District |
| Let / began | 2025-09-04 / 2026-01-28 |
| Latest estimate | 2026-10-02 |
| Contract number | 9254001 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.