# Ibctx, LLC: TxDOT interchange (new or reconstructed) contract 56% complete, IH 35E, Dallas County ($18,050,739, 14 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Ibctx, LLC |
| Subcontractors | Highway Intelligent Traffic Solutions, LLC (0%); Axis Contracting, INC. (9.79%); Jr West Texas Concrete LLC (18.88%); Southwest Road & Safety Contractors, LTD. (0.49%); USA Swppp Inspections, INC. (1.78%); Superior Traffic Control, LLC (0.31%); Beaird Drilling Services, INC. (0.76%); Mels Electric, L.P. (8.49%); Trp Construction Group, LLC (0.38%); Oscar Orduno, INC. (3.07%); Peachtree Construction, LTD. (7.61%); S&S Bridge Painting (0.12%); Penhall Company (0.07%); Emery Sapp & Son's INC. (0.07%) |
| Progress | 56.16% complete, 89.14% of time used |
| Amount | $18,050,739 revised (original $16,449,139) |
| Paid to date | $9,238,530 |
| Work | Interchange (New Or Reconstructed) |
| Location | IH 35E, AT BEAR CREEK ROAD to ., Dallas County, Dallas District |
| Let / began | 2025-03-05 / 2025-07-07 |
| Latest estimate | 2026-10-05 |
| Contract number | 3253205 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.