# Icos Management, LLC: TxDOT bridge widening or rehabilitation contract 76% complete, US 84, Coleman County ($2,817,615, 7 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Icos Management, LLC |
| Subcontractors | Sj&J Construction, LLC (3.75%); Texas Cutting & Coring, LP (0.18%); Texco Services, LLC (8.76%); Fc Traffic Control, INC. (1.05%); Stone River Bridge, LLC (41.77%); Jg&D Construction Services LLC (2.81%); Trp Construction Group, LLC (1.78%) |
| Progress | 75.76% complete, 139.25% of time used |
| Amount | $2,817,615 revised (original $2,768,115) |
| Paid to date | $2,097,167 |
| Work | Bridge Widening Or Rehabilitation |
| Location | US 84, US 84 At HORDS CREEK to various locations, Coleman County, Brownwood District |
| Let / began | 2024-10-01 / 2025-04-25 |
| Latest estimate | 2026-09-29 |
| Contract number | 10243017 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.