# Icos Management, LLC: TxDOT bridge widening or rehabilitation contract 95% complete, Various, Mclennan County ($3,259,037, 2 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Icos Management, LLC |
| Subcontractors | Fc Traffic Control, INC. (1.45%); Stone River Bridge, LLC (6.87%) |
| Progress | 95.05% complete, 99.63% of time used |
| Amount | $3,259,037 revised (original $3,067,458) |
| Change orders | $191,579 |
| Paid to date | $3,097,592 |
| Work | Bridge Widening Or Rehabilitation |
| Location | Various, VARIOUS LOCATIONS IN to BELL,BOSQUE,CORYELL,HAMILTON,HILL,FALLS & LIMESTONE COUNTIES, Mclennan County, Waco District |
| Let / began | 2025-04-04 / 2025-07-24 |
| Latest estimate | 2026-10-01 |
| Contract number | 4253218 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.