# Icos Management, LLC: TxDOT overlay contract 10% complete, FM 548, Rockwall County ($3,478,845, 8 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Icos Management, LLC |
| Subcontractors | Southern Cross Contractors, LLC (3.23%); Dallas Lite And Barricade, INC. (4.26%); Linear Traffic Markings LLC (2.79%); Buyers Barricades, INC. (0.89%); Professional Traffic Control LLC (0.6%); Flex Supply, LLC (0.45%); Catocon, INC. (1.9%); Paniolo Construction Services, LLC (11.11%) |
| Progress | 9.96% complete, 19.12% of time used |
| Amount | $3,478,845 revised (original $3,381,745) |
| Paid to date | $336,752 |
| Work | Overlay |
| Location | FM 548, SH 276 to SH 205, Rockwall County, Dallas District |
| Let / began | 2026-04-08 / 2026-09-08 |
| Latest estimate | 2026-10-02 |
| Contract number | 4263217 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.