# Icos Management, LLC: TxDOT hazard elimination & safety contract 21% complete, US 87, Victoria County ($3,630,774, 2 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Icos Management, LLC |
| Subcontractors | Highway Barricades And Services, LLC (2.01%); Stone River Bridge, LLC (44%) |
| Progress | 21.42% complete, 33.33% of time used |
| Amount | $3,630,774 revised (original $3,607,164) |
| Paid to date | $772,695 |
| Work | Hazard Elimination & Safety |
| Location | US 87, BU 77S (NAVARRO ST) to US 87 (MAIN ST), Victoria County, Yoakum District |
| Let / began | 2025-09-05 / 2026-04-06 |
| Latest estimate | 2026-10-05 |
| Contract number | 9253220 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.