# (Inactive)highway Intelligent Traffic Solutions, INC.: TxDOT miscellaneous construction contract 100%+ complete, VA, Tarrant County ($3,236,449, 5 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | (Inactive)highway Intelligent Traffic Solutions, INC. |
| Subcontractors | Superior Traffic Control, LLC (0.19%); Ransom Drilling Services, LLC (0%); Grovecrest Construction LLC (0.52%); Southern Cross Contractors, LLC (0.49%); Khonsu Enterprise LLC (4.2%) |
| Progress | 106.9% complete, 92.63% of time used |
| Amount | $3,236,449 revised (original $2,216,192) |
| Change orders | $1,016,472 |
| Paid to date | $3,455,772 |
| Work | Miscellaneous Construction |
| Location | VA, VARIOUS LOCATIONS IN TARRANT CO to ., Tarrant County, Fort Worth District |
| Let / began | 2021-08-05 / 2023-05-09 |
| Latest estimate | 2026-09-30 |
| Contract number | 8213251 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.