# (Inactive)main Lane Industries LTD.: TxDOT bridge replacement contract 97% complete, FM 109, Colorado County ($7,071,020, 16 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | (Inactive)main Lane Industries LTD. |
| Subcontractors | A. L. Helmcamp, INC. (0.16%); Siren Steel, INC. (1.26%); (Inactive)aaron Concrete Contractors, L.P. (1.79%); Lonestar Traffic Safety, LLC (0.13%); Houston Sawing & Drilling (0.18%); Cold Creek Construction, LTD (0.53%); Cornerstone Paving And Construction, L.L.C. (10.3%); Diibs Specialists, LLC (0.94%); Hunter Demolition & Wrecking Corporation (2.75%); M & D Foundation Drilling Industries, INC. (9.56%); (Inactive)mesa Rod Busters, INC. (0.54%); Highway 1 LLC (0.61%); Quality Turf Farms, L.C. (0.81%); Farr Foundation, INC. (1.06%); Mtam Corporation (0.06%); J.Kru Land Services, LLC (0.28%) |
| Progress | 96.67% complete, 97.56% of time used |
| Amount | $7,071,020 revised (original $6,985,517) |
| Paid to date | $6,752,733 |
| Work | Bridge Replacement |
| Location | FM 109, AT CUMMINS CR. & CUMMINS CR. RELIEF to STR # 0716-02-015 & 016, Colorado County, Yoakum District |
| Let / began | 2022-02-04 / 2022-07-05 |
| Latest estimate | 2026-10-05 |
| Contract number | 2223203 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.