# Indus Road & Bridge, INC.: TxDOT widen freeway contract 99% complete, US 75, Grayson County ($148,252,983, 21 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Indus Road & Bridge, INC. |
| Subcontractors | Hermanos Steel, LLC (0.71%); Fortson Contracting, INC. (0.21%); Jb Pinnacle Group, LLC (0.54%); Fc Traffic Control, INC. (0.08%); Wims Environmental Construction, LTD. (0.75%); Oscar Orduno, INC. (3.14%); Texop Construction (0.14%); Traffic Highway Maintenance, LLC (0.62%); North Texas Contracting, INC. (6.7%); Southeast Grinding And Grooving LLC (0.05%); Wylie Drilling & Drainage, INC. (2.11%); Mica Corporation (4.38%); Imt Construction, LLC (0%); Durable Specialties, INC. (1.28%); Breda Company, INC. (0.02%); Texas Auger Boring LLC (0%); Toro Bravo Construction, LLC (0%); Overland Corporation (5.22%); Scott Derr Painting Co, LLC (0.15%); Act Saw Cutting & Removal (0.32%); Hdw Construction & Drilling, LLC. (0%) |
| Progress | 99.01% complete, 80.3% of time used |
| Amount | $148,252,983 revised (original $145,430,024) |
| Change orders | $2,261,754 |
| Paid to date | $146,223,410 |
| Work | Widen Freeway |
| Location | US 75, US 75 FROM US 82 TO SH 91, Grayson County, Paris District |
| Let / began | 2024-10-01 / 2025-02-20 |
| Latest estimate | 2026-10-05 |
| Contract number | 10243031 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.