# Indus Road & Bridge, INC.: TxDOT widen freeway contract 32% complete, IH 35, Denton County ($130,758,784, 20 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Indus Road & Bridge, INC. |
| Subcontractors | North Texas Contracting, INC. (11.94%); Jb Pinnacle Group, LLC (0.71%); Stripe-A-Zone, LLC (0.37%); Overland Corporation (9.77%); USA Swppp Inspections, INC. (1.63%); Texop Construction (0.43%); Antigo Construction, INC. (0.17%); Fortson Contracting, INC. (0.1%); Mica Corporation (2.4%); Fc Traffic Control, INC. (0.1%); Wylie Drilling & Drainage, INC. (0.32%); Toro Bravo Construction, LLC (0%); Straight Line Sawing & Sealing, INC. (0.1%); Act Saw Cutting & Removal (0.11%); J.H. Painting Company (0.15%); Legacy Construction Management Services, LLC (2.74%); Houston Sawing & Drilling (0.03%); Oscar Orduno, INC. (0%); Professional Traffic Control LLC (0.02%); H Torres Trucking, L.L.C. (0.07%) |
| Progress | 32.39% complete, 20.53% of time used |
| Amount | $130,758,784 revised (original $128,704,134) |
| Change orders | $115,350 |
| Paid to date | $41,726,294 |
| Work | Widen Freeway |
| Location | IH 35, DENTON COUNTY LINE to NORTH OF FM 3002, Denton County, Dallas District |
| Let / began | 2025-08-07 / 2026-02-09 |
| Latest estimate | 2026-10-02 |
| Contract number | 8253001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.