# Ioc Company LLC: TxDOT widen non-freeway contract 100%+ complete, US 83, Starr County ($27,674,440, 17 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Ioc Company LLC |
| Subcontractors | Weber-Balke Foundation Company, INC (1.31%); Rio Grande Rebar Rodbusters, LLC (0.1%); Toro Bravo Construction, LLC (0%); *austin Traffic Signal Construction Co., INC. (0.28%); American Fence (0.27%); Texas Icon Construction, LLC (1.61%); Flovera Construction Services, LLC (4.82%); J N K Advance Tree Service (0%); Texas Highway Systems, INC. (0.21%); Laredo Striping, INC. (1.19%); Highway Barricades And Services, LLC (1.32%); Scott Derr Painting Co, LLC (0.02%); Gulf Coast Contractors, INC. (0.27%); Williams Road, LLC (0.1%); Penhall Company (0.04%); Elitecurb & Concrete, LLC (0.21%); Izaguirre Construction LLC (0.05%) |
| Progress | 100.13% complete, 100% of time used |
| Amount | $27,674,440 revised (original $24,806,299) |
| Change orders | $2,868,142 |
| Paid to date | $27,710,929 |
| Work | Widen Non-Freeway |
| Location | US 83, .255 MI NORTH OF STARR/ZAPATA CL to .31 MI NORTH OF FM 2098 (SOUTH LEG), Starr County, Pharr District |
| Let / began | 2021-12-02 / 2022-02-22 |
| Latest estimate | 2026-10-02 |
| Contract number | 12213203 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.