# Ioc Company LLC: TxDOT overlay contract 58% complete, FM 493, Hidalgo County ($11,727,548, 3 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Ioc Company LLC |
| Subcontractors | D&G Energy Corporation (0.64%); Texas Highway Systems, INC. (0.09%); Highway Barricades And Services, LLC (3.64%) |
| Progress | 57.64% complete, 53.75% of time used |
| Amount | $11,727,548 revised (original $11,224,907) |
| Paid to date | $6,470,175 |
| Work | Overlay |
| Location | FM 493, SH 107 to IH 2, Hidalgo County, Pharr District |
| Let / began | 2025-12-02 / 2026-02-16 |
| Latest estimate | 2026-10-02 |
| Contract number | 12253011 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.