# Ioc Company LLC: TxDOT hazard elimination & safety contract 21% complete, SH 48, Cameron County ($4,871,749, 5 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Ioc Company LLC |
| Subcontractors | Laredo Striping, INC. (2.25%); *austin Traffic Signal Construction Co., INC. (4.44%); Texas Highway Systems, INC. (0.69%); Soil Tech Advance INC. (0.56%); Highway Barricades And Services, LLC (6.98%) |
| Progress | 20.66% complete, 99.5% of time used |
| Amount | $4,871,749 revised (original $4,549,749) |
| Paid to date | $939,770 |
| Work | Hazard Elimination & Safety |
| Location | SH 48, SH 4 to FM 511, Cameron County, Pharr District |
| Let / began | 2024-01-05 / 2024-04-01 |
| Latest estimate | 2026-10-01 |
| Contract number | 1243218 |

## Why this score
- Contract over $1M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.