# Ioc Company LLC: TxDOT upgrade to standards freeway contract 33% complete, US 281, Hidalgo County ($169,156,689, 14 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Ioc Company LLC |
| Subcontractors | Rio Grande Rebar Rodbusters, LLC (0%); Munoz Foundation Drilling, INC. (0.16%); R. L. Abatement, INC. (0.14%); Izaguirre Construction LLC (1.3%); Laredo Striping, INC. (1.16%); Texas Icon Construction, LLC (1.54%); Texas Highway Systems, INC. (0.01%); A. H. Beck Foundation Co., INC. (0.39%); Highway Barricades And Services, LLC (0.59%); Penhall Company (0.02%); Traf-Tex, INC. (4.06%); Certified Placers LLC (0.07%); Environmental Tree And Design, INC. (0.05%); Scott Derr Painting Co, LLC (0.14%) |
| Progress | 32.56% complete, 49.06% of time used |
| Amount | $169,156,689 revised (original $165,009,689) |
| Paid to date | $53,719,977 |
| Work | Upgrade To Standards Freeway |
| Location | US 281, 0.273 MI S OF SH 186 to 0.023 MI N OF FM 490, Hidalgo County, Pharr District |
| Let / began | 2025-01-07 / 2025-06-02 |
| Latest estimate | 2026-10-06 |
| Contract number | 1253001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.