# Isi Contracting, INC.: TxDOT maintenance contract 100%+ complete, SL0008, Harris County ($5,260,517, 1 sub)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Isi Contracting, INC. |
| Subcontractors | Theweldlab Contractors LLC (0.29%) |
| Progress | 169.83% complete, 93.77% of time used |
| Amount | $5,260,517 revised (original $5,260,515) |
| Paid to date | $8,933,756 |
| Work | Maintenance |
| Location | SL0008, VARIOUS HIGHWAYS IN SOUTHEAST HARRI, Harris County, Houston District |
| Let / began | 2024-03-06 / 2024-06-10 |
| Latest estimate | 2026-10-02 |
| Contract number | 3244211 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.