# Isi Contracting, INC.: TxDOT bridge replacement contract 74% complete, US 190, Tyler County ($38,202,790, 8 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Isi Contracting, INC. |
| Subcontractors | Toro Bravo Construction, LLC (0.51%); Romar Unlimited, INC. (4.31%); Tom-Mac, INC. (4.32%); Tolunay-Wong Engineers, INC. (0.01%); Epoxy Design Systems, INC. (0.04%); Traffic Signs & Lines, LLC (0.21%); Choice Pipeline Services, LLC (3.09%); Jb Pinnacle Group, LLC (1.18%) |
| Progress | 73.96% complete, 125.41% of time used |
| Amount | $38,202,790 revised (original $37,497,101) |
| Change orders | $705,689 |
| Paid to date | $28,254,854 |
| Work | Bridge Replacement |
| Location | US 190, AT NECHES RIVER RELIEF to (STR 202290021307066), Tyler County, Beaumont District |
| Let / began | 2023-06-28 / 2024-06-14 |
| Latest estimate | 2026-10-02 |
| Contract number | 6233605 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.