# Isi Contracting, INC.: TxDOT maintenance contract 91% complete, US0290, Harris County ($5,440,477, 2 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Isi Contracting, INC. |
| Subcontractors | Structural Integrity Group LLC (4.95%); Uretek USA, INC. (0%) |
| Progress | 90.87% complete, 74.56% of time used |
| Amount | $5,440,477 revised (original $1,979,425) |
| Change orders | $3,461,050 |
| Paid to date | $4,943,690 |
| Work | Maintenance |
| Location | US0290, VARIOUS LOCATIONS IN WEST HARRIS CO to VARIOUS LOCATION IN WEST HARRIS COU, Harris County, Houston District |
| Let / began | 2023-08-02 / 2023-10-02 |
| Latest estimate | 2026-10-06 |
| Contract number | 8234028 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.