# J. Carroll Weaver, INC.: TxDOT hazard elimination & safety contract 97% complete, SH 234, San Patricio County ($6,002,457, 5 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | J. Carroll Weaver, INC. |
| Subcontractors | Avila And Son's L.L.C. (6.4%); Highway Barricades And Services, LLC (2.01%); Brooke Paving And Construction LLC (5.18%); Taylor Bridge LLC (0.33%); Performance Equipment Service (0.46%) |
| Progress | 96.51% complete, 140.63% of time used |
| Amount | $6,002,457 revised (original $5,492,231) |
| Change orders | $510,225 |
| Paid to date | $5,793,024 |
| Work | Hazard Elimination & Safety |
| Location | SH 234, ON SH234 FROM IH37SB FRTG to CR 1969, San Patricio County, Corpus Christi District |
| Let / began | 2024-03-05 / 2024-11-11 |
| Latest estimate | 2026-10-02 |
| Contract number | 3243013 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.