# J. Carroll Weaver, INC.: TxDOT bridge replacement contract 97% complete, CR, Webb County ($4,522,095, 4 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | J. Carroll Weaver, INC. |
| Subcontractors | Avila And Son's L.L.C. (10.19%); Munoz Foundation Drilling, INC. (3.82%); Soil Tech Advance INC. (3.45%); Highway Barricades And Services, LLC (0.99%) |
| Progress | 96.63% complete, 82.06% of time used |
| Amount | $4,522,095 revised (original $4,378,550) |
| Change orders | $143,545 |
| Paid to date | $4,369,747 |
| Work | Bridge Replacement |
| Location | CR, LINCOLN ROAD to ., Webb County, Laredo District |
| Let / began | 2024-06-05 / 2024-11-18 |
| Latest estimate | 2026-10-05 |
| Contract number | 6243049 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.