# J. H. Strain & Sons, INC.: TxDOT bridge replacement contract 98% complete, CR, Runnels County ($2,144,186, 5 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | J. H. Strain & Sons, INC. |
| Subcontractors | Contractors Service, LTD. (2.56%); Diibs Specialists, LLC (4.68%); M & D Foundation Drilling Industries, INC. (4.14%); Emery Sapp & Son's INC. (0.24%); Thornton's Tree Service, INC. (1.63%) |
| Progress | 98% complete, 91.3% of time used |
| Amount | $2,144,186 revised (original $1,997,089) |
| Change orders | $147,097 |
| Paid to date | $2,101,261 |
| Work | Bridge Replacement |
| Location | CR, ON CR 331 OVER WEST FORK BRANCH to 0.5 MILES NORTH OF CR 262, Runnels County, San Angelo District |
| Let / began | 2025-01-08 / 2025-04-28 |
| Latest estimate | 2026-10-06 |
| Contract number | 1253227 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.