# J. Lee Milligan, INC.: TxDOT rehabilitation of existing road contract 61% complete, US 54, Dallam County ($26,623,978, 5 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | J. Lee Milligan, INC. |
| Subcontractors | Alamo Brothers Concrete INC (5.48%); Apollo Constructors, INC. (1.81%); Hjc Farms, INC. (1.02%); Trp Construction Group, LLC (1.1%); Wolfe Construction Group, Incorporated (0.17%) |
| Progress | 61.09% complete, 45.34% of time used |
| Amount | $26,623,978 revised (original $25,914,961) |
| Change orders | $703,018 |
| Paid to date | $16,261,526 |
| Work | Rehabilitation Of Existing Road |
| Location | US 54, HARTLEY COUNTY LINE to US 87, Dallam County, Amarillo District |
| Let / began | 2024-10-01 / 2025-08-11 |
| Latest estimate | 2026-10-05 |
| Contract number | 10243005 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.