# J. Lee Milligan, INC.: TxDOT widen freeway contract 100% complete, FM 281, Moore County ($41,423,505, 4 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | J. Lee Milligan, INC. |
| Subcontractors | Hjc Farms, INC. (0.44%); Surface Preparation Technologies, LLC (0.07%); Trp Construction Group, LLC (0.8%); Wolfe Construction Group, Incorporated (0.11%) |
| Progress | 99.86% complete, 98.87% of time used |
| Amount | $41,423,505 revised (original $41,097,397) |
| Change orders | $-210,928 |
| Paid to date | $40,828,659 |
| Work | Widen Freeway |
| Location | FM 281, HARTLEY COUNTY LINE to US 287, Moore County, Amarillo District |
| Let / began | 2024-02-02 / 2024-07-08 |
| Latest estimate | 2026-10-05 |
| Contract number | 2243203 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.