# J. Lee Milligan, INC.: TxDOT maintenance contract 57% complete, IH0040, Potter County ($10,007,611)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | J. Lee Milligan, INC. |
| Progress | 57.47% complete, 99.62% of time used |
| Amount | $10,007,611 revised (original $6,977,100) |
| Change orders | $3,030,511 |
| Paid to date | $5,751,786 |
| Work | Maintenance |
| Location | IH0040, General Maintenance Amarillo AE FY 24 to VARIOUS LOCATIONS ~ SEE PLAN SHEETS, Potter County, Amarillo District |
| Let / began | 2024-02-02 / 2024-04-18 |
| Latest estimate | 2026-09-02 |
| Contract number | 2244231 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.