# J. Lee Milligan, INC.: TxDOT hazard elimination & safety contract 56% complete, FM 2590, Randall County ($28,568,456, 7 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | J. Lee Milligan, INC. |
| Subcontractors | W. S. Construction Company (13.84%); Wolfe Construction Group, Incorporated (0.08%); Surface Preparation Technologies, LLC (0.08%); Trp Construction Group, LLC (0.95%); King George Traffic Solutions LLC (0.21%); Apollo Constructors, INC. (5.32%); Hjc Farms, INC. (0.92%) |
| Progress | 56.42% complete, 126.21% of time used |
| Amount | $28,568,456 revised (original $28,487,051) |
| Change orders | $65,405 |
| Paid to date | $16,109,773 |
| Work | Hazard Elimination & Safety |
| Location | FM 2590, SL 335 to US 60 (CANYON), Randall County, Amarillo District |
| Let / began | 2024-06-05 / 2024-12-02 |
| Latest estimate | 2026-10-06 |
| Contract number | 6243005 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.