# J. Lee Milligan, INC.: TxDOT rehabilitation of existing road contract 15% complete, US 60, Deaf Smith County ($45,199,631, 5 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | J. Lee Milligan, INC. |
| Subcontractors | Wolfe Construction Group, Incorporated (0.02%); Trp Construction Group, LLC (1.33%); Alamo Brothers Concrete INC (9.54%); Hjc Farms, INC. (0.5%); Apollo Constructors, INC. (2.17%) |
| Progress | 14.6% complete, 17.81% of time used |
| Amount | $45,199,631 revised (original $44,993,689) |
| Change orders | $192,942 |
| Paid to date | $6,598,114 |
| Work | Rehabilitation Of Existing Road |
| Location | US 60, DIVIDED 4 LANE to US 385, Deaf Smith County, Amarillo District |
| Let / began | 2025-06-04 / 2026-03-09 |
| Latest estimate | 2026-10-06 |
| Contract number | 6253003 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.