# Jagoe-Public Company: TxDOT rehabilitation of existing road contract 89% complete, FM 920, Parker County ($4,997,477, 5 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Jagoe-Public Company |
| Subcontractors | Trp Construction Group, LLC (2.91%); Dustrol, INC. (9.45%); Superior Traffic Control, LLC (0.66%); Southern Cross Contractors, LLC (0.27%); Civil Tree Solutions, LLC (0.07%) |
| Progress | 88.56% complete, 84.55% of time used |
| Amount | $4,997,477 revised (original $5,006,549) |
| Change orders | $-9,079 |
| Paid to date | $4,425,696 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 920, RIC WILLIAMSON to FM 51, Parker County, Fort Worth District |
| Let / began | 2025-10-09 / 2026-03-02 |
| Latest estimate | 2026-10-06 |
| Contract number | 10253213 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.