# Jagoe-Public Company: TxDOT widen non-freeway contract 100%+ complete, US 377, Grayson County ($7,318,307, 7 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Jagoe-Public Company |
| Subcontractors | Trp Construction Group, LLC (0.61%); Dustrol, INC. (1.83%); North Texas Traffic Systems Construction (5.36%); Diibs Specialists, LLC (0.35%); Marcoms Construction LLC (0.51%); J. H. Oden Contracting Company (1.51%); Texas Environmental Management - San Antonio, INC. (3.86%) |
| Progress | 101.08% complete, 56.57% of time used |
| Amount | $7,318,307 revised (original $6,968,771) |
| Change orders | $-23,476 |
| Paid to date | $7,020,024 |
| Work | Widen Non-Freeway |
| Location | US 377, US 377 FROM 0.3 MI S OF FM 922 TO 0.3 MI N OF MCKNIGHT RD, Grayson County, Paris District |
| Let / began | 2025-03-04 / 2025-06-02 |
| Latest estimate | 2026-10-05 |
| Contract number | 3253034 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.