# Jagoe-Public Company: TxDOT widen non-freeway contract 100%+ complete, FM 373, Cooke County ($7,336,794, 8 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Jagoe-Public Company |
| Subcontractors | Mobile Enterprises, INC. (0.13%); Traffic Highway Maintenance, LLC (1.51%); Surface Preparation Technologies, LLC (0.4%); Texop Construction (2.4%); Joe's Tree Service (0.87%); J. H. Oden Contracting Company (0.87%); Dustin Allen, INC. (1.14%); Marcoms Construction LLC (0.44%) |
| Progress | 102.09% complete, 47.33% of time used |
| Amount | $7,336,794 revised (original $7,282,548) |
| Change orders | $43,446 |
| Paid to date | $7,479,166 |
| Work | Widen Non-Freeway |
| Location | FM 373, DRY ELM CREEK to CR 485, Cooke County, Wichita Falls District |
| Let / began | 2025-06-04 / 2025-08-11 |
| Latest estimate | 2026-10-01 |
| Contract number | 6253007 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.