# Jagoe-Public Company: TxDOT rehabilitation of existing road contract 94% complete, FM 3163, Denton County ($4,266,792, 9 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Jagoe-Public Company |
| Subcontractors | J. H. Oden Contracting Company (4.12%); Mobile Enterprises, INC. (1.21%); Dustin Allen, INC. (0.7%); S & S Bridge Painting, INC. (1.32%); Synergy Signs & Services LLC (0.34%); Trp Construction Group, LLC (0.88%); Superior Traffic Control, LLC (0.31%); Dustrol, INC. (0.44%); Texas Environmental Management - San Antonio, INC. (5.88%) |
| Progress | 94.27% complete, 94.49% of time used |
| Amount | $4,266,792 revised (original $4,145,279) |
| Change orders | $16,513 |
| Paid to date | $3,923,449 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 3163, IH 35 to FM 2164, Denton County, Dallas District |
| Let / began | 2025-09-05 / 2025-12-02 |
| Latest estimate | 2026-10-02 |
| Contract number | 9253219 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.