# James Construction Group, LLC: TxDOT widen non-freeway contract 93% complete, SH 105, Montgomery County ($105,018,262, 19 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Allstate Signal & Construction, LLC (3.28%); Willow City Sign & Rail, INC. (0.73%); Stripe Lines, INC. (0.06%); J. T. B. Services, INC. (0.24%); Aviles Construction Service, INC (0.21%); Williams Road, LLC (0.91%); Vulcan Materials Asphalt And Construction, LLC (5.97%); Bls Services (0.08%); Valley Placers, LLC (0.19%); Who-B Trucking, INC. (3.35%); Durwood Greene Construction Co. (5.97%); J.Kru Land Services, LLC (0.01%); Professional Traffic Control LLC (0.7%); (Inactive)mesa Rod Busters, INC. (0.86%); Texas Environmental Management - San Antonio, INC. (1.4%); Southeast Grinding And Grooving LLC (0.07%); Curb Planet INC. (0.04%); Texas Sterling Construction Co. (2.19%); Sk Concrete Services LLC (0.27%) |
| Progress | 92.91% complete, 98.95% of time used |
| Amount | $105,018,262 revised (original $107,298,495) |
| Change orders | $-2,280,240 |
| Paid to date | $97,575,461 |
| Work | Widen Non-Freeway |
| Location | SH 105, FM 1484 to SAN JACINTO COUNTY LINE, Montgomery County, Houston District |
| Let / began | 2022-10-06 / 2023-05-30 |
| Latest estimate | 2026-10-01 |
| Contract number | 10223001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.