# James Construction Group, LLC: TxDOT miscellaneous construction contract 23% complete, US 83, Taylor County ($74,023,914, 14 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Fc Traffic Control, INC. (0.15%); Tex Op Construction, LP (0.58%); Sk Concrete Services LLC (0.03%); Trp Construction Group, LLC (0.8%); Wolfe Construction Group, Incorporated (0.23%); Professional Traffic Control LLC (0.01%); 2h, LLC (0.89%); M & D Foundation Drilling Industries, INC. (1.23%); G & L Rebar (0.36%); Lone Star Paving Company (15.79%); Light It Up Electric (4.15%); J. H. Strain & Sons, INC. (0.07%); 4-Way Haulers, LLC (4.9%); Toro Bravo Construction, LLC (0.05%) |
| Progress | 23.18% complete, 12.75% of time used |
| Amount | $74,023,914 revised (original $72,482,832) |
| Paid to date | $16,798,249 |
| Work | Miscellaneous Construction |
| Location | US 83, AT to US 83/84 "Y" INTERCHANGE, Taylor County, Abilene District |
| Let / began | 2025-10-08 / 2026-04-08 |
| Latest estimate | 2026-10-06 |
| Contract number | 10253001 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.