# James Construction Group, LLC: TxDOT widen non-freeway contract 34% complete, US 190, Madison County ($183,820,507, 16 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Statewide Materials Transport, LTD. (6.27%); West Texas Rumble Strip LLC (0.04%); G-Iron Logistics LLC (1.2%); Williams Road, LLC (0.5%); Mesa Rod Busters INC (0.1%); Knife River Corporation - South (18.19%); M & D Foundation Drilling Industries, INC. (1.22%); Toro Bravo Construction, LLC (0.06%); Third Coast Services LLC (0.37%); Sk Concrete Services LLC (0.04%); Lonestar Traffic Safety, LLC (0.2%); Who-B Trucking, INC. (1.16%); Trp Construction Group, LLC (0.93%); Brock Construction, LLC (0.74%); J. H. Oden Contracting Company (2.11%); Willow City Sign & Rail, INC. (0.62%) |
| Progress | 34.09% complete, 22.7% of time used |
| Amount | $183,820,507 revised (original $178,956,172) |
| Change orders | $1,170,045 |
| Paid to date | $61,408,023 |
| Work | Widen Non-Freeway |
| Location | US 190, BRAZOS COUNTY LINE to 1 MI EAST OF FM 39, Madison County, Bryan District |
| Let / began | 2024-11-07 / 2025-07-07 |
| Latest estimate | 2026-09-30 |
| Contract number | 11243201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.