# James Construction Group, LLC: TxDOT widen non-freeway contract 98% complete, SL 363, Bell County ($55,332,401, 30 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Miller Springs Materials, L.L.C. (0.72%); Texop Construction (0.01%); Gk Construction, LLC (0%); Primate Construction, LP (0.03%); Sk Concrete Services LLC (0.15%); Speedy Paving (0.32%); F & W Electrical Contractors, INC. (2.54%); Fortson Contracting, INC. (0.78%); Aaron Concrete Contractors, LLC (0.44%); Wims Environmental Construction, LTD. (0.34%); Lone Star Paving Company (3.81%); Texas Traffic And Barricade, LLC (0.17%); Rucoba & Maya Construction, LLC (1.63%); Texas Solutions Trucking, INC. (0.52%); Texas Cutting & Coring Gp, INC. (0.1%); Penhall Company (0.41%); Beaird Drilling Services, INC. (0.99%); Royal Rebar INC (0%); Gordillo Transportation INC (0.47%); Pinnacle Grinding And Grooving LLC (0.5%); Southwest Road & Safety Contractors, LTD. (0.58%); Statewide Materials Transport, LTD. (0.09%); Reynaldo H Ortiz LLC (2.01%); Trp Construction Group, LLC (0.52%); Texas Clear Cut LLC (5.84%); Hayden Concrete, INC. (0%); Trinity Site Construction, LLC (1.1%); Hermanos Steel, LLC (4.11%); Professional Traffic Control LLC (0.11%); Southeast Grinding And Grooving LLC (0.07%) |
| Progress | 98.05% complete, 96.48% of time used |
| Amount | $55,332,401 revised (original $53,775,775) |
| Change orders | $1,556,626 |
| Paid to date | $54,251,784 |
| Work | Widen Non-Freeway |
| Location | SL 363, INDUSTRIAL BLVD to LUCIUS MCCELVEY, Bell County, Waco District |
| Let / began | 2024-02-02 / 2024-06-03 |
| Latest estimate | 2026-10-01 |
| Contract number | 2243201 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.