# James Construction Group, LLC: TxDOT miscellaneous construction contract 98% complete, MH, Harris County ($59,329,283, 30 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | (Inactive)ar Daniel Construction Services, INC. (2%); J.H. Painting Company (0.14%); (Inactive)primate Construction, INC. (0.11%); R & R Concrete Contractors, INC. (6.86%); Texas Environmental Management - San Antonio, INC. (0.27%); Third Coast Services LLC (1.53%); Willow City Sign & Rail, INC. (0.07%); Rosales R Trucking, LLC (1.93%); W.W. Foundation Drilling, LTD. (8.09%); Choctaw Erectors, INC. (6.96%); Highway 1 LLC (0.25%); (Inactive)peltier Brothers Construction, LTD. (12.86%); Lonestar Traffic Safety, LLC (0.1%); Doran Steel, INC. (0.46%); Eubank Excavation, L.L.C. (0.08%); Harbour Contractors, INC. (6.89%); Semarck Landscape Services, INC. (0.61%); Southwest Road & Safety Contractors, LTD. (0.4%); Texas Moisture Protection Company (0.46%); Howard Pile Driving Company, INC. (0.92%); Curb Planet INC. (0.02%); Electric Control & Service, INC. (0.67%); Sowells Consulting Engineers, LLC (0.22%); Isj Underground Utilities LLC (0.26%); Buyers Barricades Houston, LLC (0.04%); Viking Fence Company, LTD. (0.03%); Texas Materials Group, INC. (0.55%); Aviles Construction Service, INC (0.16%); Trp Construction Group, LLC (0.25%); Southeast Grinding And Grooving LLC (0.07%) |
| Progress | 98.27% complete, 165.27% of time used |
| Amount | $59,329,283 revised (original $49,926,140) |
| Change orders | $3,897,242 |
| Paid to date | $52,893,139 |
| Work | Miscellaneous Construction |
| Location | MH, ON HEMPSTEAD RD, 0.059 MI W OF 12 to ST TO E OF WASHINGTON-KATY SPLIT, Harris County, Houston District |
| Let / began | 2017-05-03 / 2018-02-20 |
| Latest estimate | 2026-09-30 |
| Contract number | 5173201 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.