# James Construction Group, LLC: TxDOT new location freeway contract 90% complete, US 59, Polk County ($178,705,269, 30 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Lonestar Traffic Safety, LLC (0.06%); Ancortex, INC. (2.12%); Allstate Signal & Construction, LLC (1.65%); Eagle Construction LLC (6.93%); Isaacs Construction Services LLC (0.25%); Morris County Contractors, L.L.C. (0.36%); Prater Dirt Work LLC (0.35%); Batterson, LLP (0.27%); Moore Brothers Construction Company (0%); West Texas Rock Resources, LLC (0.04%); Ccc Blacktopping LLC (0.45%); J.H. Painting Company (0.16%); Texas Environmental Management - San Antonio, INC. (0.6%); Willow City Sign & Rail, INC. (0.08%); J & M Contracting, Company (2.04%); Ray's Threading And Fab Shop (0.23%); Primate Construction, LP (0.23%); Choctaw Erectors, INC. (0.41%); B & N Logging, LLC (0.01%); Little Beauchamp Trucking (0%); J. H. Oden Contracting Company (0.07%); Texas Materials Group, INC. (8.42%); Penhall Company (0.01%); Graham Resources, LLC (0.13%); A&J Rebar LLC (0.81%); Batten Drilling, INC. (0.1%); Mtam Corporation (0.09%); Texas Solutions Trucking, INC. (0.09%); Dustrol, INC. (0.2%); Southeast Grinding And Grooving LLC (0.03%) |
| Progress | 90.03% complete, 88.8% of time used |
| Amount | $178,705,269 revised (original $172,799,108) |
| Change orders | $5,900,161 |
| Paid to date | $160,889,540 |
| Work | New Location Freeway |
| Location | US 59, 3.4 MI N OF US 287 to US 287, Polk County, Lufkin District |
| Let / began | 2022-05-05 / 2022-10-03 |
| Latest estimate | 2026-10-05 |
| Contract number | 5223201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.