# James Construction Group, LLC: TxDOT widen freeway contract 34% complete, SH 146, Galveston County ($200,589,211, 32 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Sk Concrete Services LLC (0.12%); Hb Farmer Foundation, LLC (4.01%); B & D Maintenance LLC (0.05%); Mtam Corporation (0.02%); Southwest Road & Safety Contractors, LTD. (0.69%); Allstate Signal & Construction, LLC (3.82%); B&D Maintenance (0.05%); A Brothers Milling, LLC (0.8%); Vera Industries, LLC (0.29%); Professional Traffic Control LLC (0.48%); Primate Construction, LP (0%); Ikon Environmental Solutions, LP (0.03%); Tetra Tech Construction Services, INC. (0.03%); G-Iron Logistics LLC (0.05%); Dw Resources, LLC (0.03%); Vulcan Materials Asphalt And Construction, LLC (8.63%); Curb Planet INC. (0.01%); Scott Derr Painting Co, LLC (0.04%); Cherry Moving Company, INC. (0.04%); Highway 1 LLC (0.07%); Trp Construction Group, LLC (0.07%); Durwood Greene Construction Co. (8.63%); Aviles Construction Service, INC (0.12%); J.Kru Land Services, LLC (0.03%); Proscape Development LLC (0.01%); C.G. Anthony Deliveries, LLC (0.05%); Badger Daylighting Corp. (0.01%); Speedy Paving (0.1%); Hermanos Steel, LLC (0.44%); Quality Turf Farms, L.C. (2.02%); Legis Elite Services, LLC (0.05%); R & B Group, INC. (1.16%) |
| Progress | 33.65% complete, 55.83% of time used |
| Amount | $200,589,211 revised (original $197,855,402) |
| Change orders | $1,193,497 |
| Paid to date | $66,988,305 |
| Work | Widen Freeway |
| Location | SH 146, FM 518 to DICKINSON BAYOU, Galveston County, Houston District |
| Let / began | 2023-05-05 / 2024-02-01 |
| Latest estimate | 2026-09-30 |
| Contract number | 5233201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.