# James Construction Group, LLC: TxDOT bridge replacement contract 64% complete, IH 20, Ward County ($29,259,684, 18 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | F.S. Trucking, INC. (1.01%); Lone Star Paving Company (10.67%); Trp Construction Group, LLC (0.54%); West Texas Rock Resources, LLC (0.02%); Jb Pinnacle Group, LLC (1.53%); Cnd Contracting, LLC (2.76%); A-Core Concrete Cutting Of Texas, INC. (0.17%); Dallas Lite And Barricade, INC. (0.75%); M & D Foundation Drilling Industries, INC. (6.59%); Fc Traffic Control, INC. (0.13%); A Brothers Milling, LLC (0.24%); Hjc Farms, INC. (1.17%); A K Fuquay Construction (0.42%); Toro Bravo Construction, LLC (0.38%); Scr Civil Construction, LLC (0.5%); Nationwide Rebar INC. (1.22%); Nelson Industrial Services, INC. (0.09%); Rubio's Paving (2.96%) |
| Progress | 63.83% complete, 94.57% of time used |
| Amount | $29,259,684 revised (original $28,745,655) |
| Change orders | $244,479 |
| Paid to date | $18,504,204 |
| Work | Bridge Replacement |
| Location | IH 20, 0.10 MI NE OF REEVES C/L (PECOS RIV to 0.25 MI SW OF FM 516, Ward County, Odessa District |
| Let / began | 2023-06-27 / 2024-01-08 |
| Latest estimate | 2026-09-30 |
| Contract number | 6233409 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.