# James Construction Group, LLC: TxDOT widen non-freeway contract 100%+ complete, FM 1097, Montgomery County ($22,238,450, 25 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Vulcan Materials Asphalt And Construction, LLC (2.06%); Sarvicus LLC (1.58%); (Inactive)j Kru Land Services, LLC (0.03%); (Inactive)mesa Rod Busters, INC. (5.06%); Cen Tex Hydroseed, INC. (0.39%); Lonestar Traffic Safety, LLC (0.12%); Sweeping Services Of Texas - Operating, L.P. (0.06%); Dustrol, INC. (0.63%); Willow City Sign & Rail, INC. (0.54%); Highway 1 LLC (0.72%); Highway Pavement Specialties, INC. (0.19%); Buyers Barricades, INC. (0%); Buyers Barricades Houston, LLC (0.07%); Tom-Mac, INC. (2.01%); Aviles Construction Service, INC (0.98%); Durwood Greene Construction Co. (0.41%); Southeast Grinding And Grooving LLC (0.21%); Larry Young Paving, INC. (0.93%); Batten Drilling, INC. (0.69%); Aggregate Technologies, INC. (0.14%); Vera Industries, LLC (0.88%); C.G. Anthony Deliveries, LLC (1.28%); Texas Environmental Management - San Antonio, INC. (0.71%); Primate Construction, LP (0.3%); Mesa Rod Busters INC (5.06%) |
| Progress | 102.51% complete, 135.86% of time used |
| Amount | $22,238,450 revised (original $16,095,271) |
| Change orders | $6,143,173 |
| Paid to date | $22,797,382 |
| Work | Widen Non-Freeway |
| Location | FM 1097, WEST OF BLUEBERRY HILLS RD to LAKE CONROE HILLS DR, Montgomery County, Houston District |
| Let / began | 2021-08-04 / 2022-01-19 |
| Latest estimate | 2026-10-01 |
| Contract number | 8213010 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.