# James Construction Group, LLC: TxDOT widen non-freeway contract 76% complete, FM 1488, Montgomery County ($49,181,533, 22 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | (Inactive)mesa Rod Busters, INC. (0.8%); Highway 1 LLC (1.28%); Dustrol, INC. (0.48%); Hb Farmer Foundation, LLC (1.68%); Third Coast Services LLC (1.97%); Willow City Sign & Rail, INC. (0.43%); Buyers Barricades, INC. (0%); Consolidated Crane & Rigging (0.1%); Durwood Greene Construction Co. (3.94%); Speedy Paving (0.42%); Curb Planet INC. (0.2%); Buyers Barricades Houston, LLC (0.09%); Isj Underground Utilities LLC (1.95%); Primate Construction, LP (0.2%); Trp Construction Group, LLC (1.3%); Cen Tex Hydroseed, INC. (1.66%); Southeast Grinding And Grooving LLC (0.1%); Mickie Service, INC. (0.29%); Vulcan Materials Asphalt And Construction, LLC (5.18%); Cpave, INC. (0.08%); P&Z Logistics INC. (0.23%); Texas Environmental Management - San Antonio, INC. (0.18%) |
| Progress | 76.2% complete, 132.64% of time used |
| Amount | $49,181,533 revised (original $48,285,564) |
| Change orders | $895,964 |
| Paid to date | $37,478,083 |
| Work | Widen Non-Freeway |
| Location | FM 1488, FM 1774 IN MAGNOLIA to WEST OF FM 149, Montgomery County, Houston District |
| Let / began | 2021-08-05 / 2022-06-14 |
| Latest estimate | 2026-10-01 |
| Contract number | 8213204 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.