# James Construction Group, LLC: TxDOT widen non-freeway contract 70% complete, SH 105, Montgomery County ($53,266,100, 19 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Vulcan Materials Asphalt And Construction, LLC (6.45%); Koppl Pipeline Services, INC (0.31%); Weber-Balke Foundation Company, INC (0.55%); Willow City Sign & Rail, INC. (0.22%); Scott Derr Painting Co, LLC (0.01%); Sarvicus LLC (1.6%); Highway 1 LLC (0.17%); Cen Tex Hydroseed, INC. (0.34%); Quality Turf Farms, L.C. (1.32%); (Inactive)mesa Rod Busters, INC. (0.62%); J. T. B. Services, INC. (0.08%); Sk Concrete Services LLC (0.27%); (Inactive)j Kru Land Services, LLC (0.14%); Vera Industries, LLC (3.92%); Curb Planet INC. (0.05%); Durwood Greene Construction Co. (5.02%); Who-B Trucking, INC. (3.42%); Professional Traffic Control LLC (0.64%); Larry Young Paving, INC. (1.6%) |
| Progress | 69.83% complete, 104.35% of time used |
| Amount | $53,266,100 revised (original $51,803,008) |
| Change orders | $1,463,086 |
| Paid to date | $37,194,071 |
| Work | Widen Non-Freeway |
| Location | SH 105, 10TH STREET to SL 336, Montgomery County, Houston District |
| Let / began | 2022-08-04 / 2023-08-28 |
| Latest estimate | 2026-10-01 |
| Contract number | 8223203 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.