# James Construction Group, LLC: TxDOT upgrade to standards freeway contract 47% complete, US 59, Webb County ($351,512,621, 21 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Rio Grande Rebar Rodbusters, LLC (0%); Primate Construction, LP (0.21%); Highway Barricades And Services, LLC (0.61%); Laredo Striping, INC. (0.34%); Uvalle & Sons Trucking LLC (0.24%); Hjc Farms, INC. (0.06%); Munoz Foundation Drilling, INC. (0%); Rk Power Drive Services, INC. (0.05%); Slaton Bros, INC. (0.23%); Texas Clear Cut LLC (0.04%); Guerra Underground LLC (4.08%); Ancortex, INC. (1.41%); Texas Materials Group, INC. (8.52%); Best Tunneling & Boring LLC (0.11%); A K Fuquay Construction (0.38%); J.H. Painting Company (0.17%); Dustrol, INC. (1.03%); Interstate Improvement, INC. (1.04%); Emery Sapp & Son's INC. (0.03%); Traf-Tex, INC. (3.58%); Hart Services LLC (0%) |
| Progress | 47.15% complete, 40.97% of time used |
| Amount | $351,512,621 revised (original $344,030,535) |
| Change orders | $7,482,086 |
| Paid to date | $165,730,285 |
| Work | Upgrade To Standards Freeway |
| Location | US 59, 0.50 MI S OF DEL MAR BLVD to 0.50 MI N OF DEL MAR BLVD, Webb County, Laredo District |
| Let / began | 2023-08-02 / 2024-02-19 |
| Latest estimate | 2026-10-05 |
| Contract number | 8233001 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.