# James Construction Group, LLC: TxDOT miscellaneous construction contract 28% complete, IH 45, Montgomery County ($43,038,118, 20 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Lightning Earthwork LLC (0.05%); R & B Group, INC. (10.99%); Vera Industries, LLC (7.7%); USA Amtech, INC. (1.83%); Primate Construction, LP (0.19%); Shaw Drilling, LLC (0.02%); Houston Crushed Concrete, L.L.C. (0.23%); Farr Foundation, INC. (0.45%); Bls Services (0.18%); Royal Rebar INC (3.15%); Willow City Sign & Rail, INC. (0.27%); Professional Traffic Control LLC (0.19%); Deco Contractors, INC. (1.19%); Scott Derr Painting Co, LLC (0.1%); Southwest Road & Safety Contractors, LTD. (0.04%); Texas Environmental Management - San Antonio, INC. (0.74%); Lonestar Traffic Safety, LLC (0.07%); Expert Gold Services, LLC (0.29%); 4e Infra Construction LLC (0.6%); P&Z Logistics INC. (0.04%) |
| Progress | 27.91% complete, 67.06% of time used |
| Amount | $43,038,118 revised (original $42,630,751) |
| Change orders | $407,362 |
| Paid to date | $12,010,282 |
| Work | Miscellaneous Construction |
| Location | IH 45, S OF SHENANDOAH PARK DR to SH 242, Montgomery County, Houston District |
| Let / began | 2024-08-02 / 2025-03-03 |
| Latest estimate | 2026-10-01 |
| Contract number | 8243202 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.