# James Construction Group, LLC: TxDOT miscellaneous construction contract 100%+ complete, SH 249, Harris County ($8,084,716, 6 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Traffic Signs & Lines, LLC (5.82%); Trp Construction Group, LLC (7.49%); Mtam Corporation (1.61%); A&J Rebar LLC (0.17%); Deco Contractors, INC. (7.33%); Shaw Drilling, LLC (0.06%) |
| Progress | 106.26% complete, 106.67% of time used |
| Amount | $8,084,716 revised (original $7,878,086) |
| Change orders | $86,628 |
| Paid to date | $8,463,494 |
| Work | Miscellaneous Construction |
| Location | SH 249, 0.2 MI. NORTH OF HOLLISTER RD. to 0.46 MI. NORTH OF GREGSON RD., Harris County, Houston District |
| Let / began | 2024-09-05 / 2025-09-02 |
| Latest estimate | 2026-09-30 |
| Contract number | 9243013 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.