# James Construction Group, LLC: TxDOT widen freeway contract 91% complete, SL 336, Montgomery County ($21,465,641, 15 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | James Construction Group, LLC |
| Subcontractors | Mesa Rod Busters INC (0.08%); Texas Environmental Management - San Antonio, INC. (4%); Professional Traffic Control LLC (1.47%); Bls Services (0.76%); Willow City Sign & Rail, INC. (0.88%); Vulcan Materials Asphalt And Construction, LLC (5.39%); Third Coast Services LLC (7.21%); Cpave, INC. (0.21%); Primate Construction, LP (0.03%); Durwood Greene Construction Co. (5.39%); Superior Traffic Control, LLC (0.16%); Scott Derr Painting Co, LLC (0.01%); M & D Foundation Drilling Industries, INC. (2.55%); (Inactive)mesa Rod Busters, INC. (0.08%); Curb Planet INC. (0.06%) |
| Progress | 91.35% complete, 91.89% of time used |
| Amount | $21,465,641 revised (original $20,568,606) |
| Change orders | $825,978 |
| Paid to date | $19,543,012 |
| Work | Widen Freeway |
| Location | SL 336, I-45 to LADERA CREEK TRACE, Montgomery County, Houston District |
| Let / began | 2024-09-06 / 2024-12-05 |
| Latest estimate | 2026-10-01 |
| Contract number | 9243205 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.